Haikou Meilan International Airport Phase Ii Expansion, Fully Promoting Resumption Of Work And Production

Full load promotion of Meilan Airport Phase II expansion project

On March 10th at 21:00, the construction site of the second phase expansion project of Haikou Meilan International Airport (hereinafter referred to as the second phase expansion project) terminal was very busy. The project leaders were holding on-site coordination meetings to discuss the daily schedule and coordinate personnel construction.

On March 6th, the Hainan Provincial Party Committee held a teleconference to fully promote the development of tourism, modern service industry, and high-tech industry, accelerating the construction of Hainan Free Trade Port. Hainan Airlines Group actively utilizes its main aviation advantages to support and serve the development of Hainan's tourism industry, quickly and deeply implements the spirit of relevant conferences, and accelerates the construction of the second phase expansion project.

Efficient linkage between government and enterprises


11111.png


Fully promote the resumption of work and production

"Thanks to the unit providing us with a certificate and using a special car to pick us up from the village and deliver us to the airport, otherwise we wouldn't know when we would be able to come back to work," said Zhang Baohong, a worker who was renovating at the construction site.

"Many of our workers' hometowns have been locked down before, and they really wanted to come back to work, but couldn't leave the village." Liang Huazhan, the construction manager of the Haikou Meilan International Airport Phase II expansion project of China Construction Eighth Bureau, told Hainan Daily reporters that due to the impact of the epidemic in the early stage, there were closed traffic restrictions in various regions, which limited the return of personnel to work after the Spring Festival, and material and equipment manufacturers were unable to produce and supply. The resumption plan for the Phase II expansion project was hindered.

To solve these difficulties, under the communication and coordination of the Provincial Party Committee, Provincial Government, Haikou Municipal Party Committee and Municipal Government, and under the overall planning of Hainan Airlines Group, the Phase II expansion project actively connects with the local government where the workers are located. By issuing work certificates to healthy workers, investing in special vehicles to pick them up, and other means, the workers can return to work as soon as possible.

In less than half a month, the number of migrant workers in the Phase II expansion project has increased from over 1000 during the Spring Festival period to nearly 2500, achieving the phased goal of personnel returning to work ahead of schedule and meeting the demand for 100% full load construction personnel.

Coordinate with suppliers

Materials and equipment entering the site on time

The material and equipment manufacturers of the Phase II expansion project are distributed in 14 provinces and cities across China, including Shanghai, Jiangsu, and Guangdong. Due to the impact of the epidemic, the resumption of work and production in the industrial chain has been delayed, resulting in the inability to carry out the fire protection system, weak current system, mechanical and electrical installation and other processes of the project normally

If the equipment cannot enter, it will be difficult to keep up with the progress of the project. To this end, with the support of Haikou City and the collaboration of all parties, a material and equipment entry coordination group has been established for the Phase II expansion project. While actively coordinating with manufacturers to resume production and supply as soon as possible, measures such as changing the brand and purchasing products of the same specifications from local manufacturers in Hainan will be taken to remedy the temporarily unavailable materials.

"At present, the second phase expansion project has successfully solved the urgent problem of materials and equipment entering the site, and can be synchronized and matched with returning workers. All working faces on the site have been fully launched, and normal construction status has been restored." said Bian Zhen, the geotechnical engineer of the terminal area engineering department of Haikou Meilan International Airport's second phase expansion project.

Seize the time to make up for the progress

Assist in the construction of free trade ports

Temperature monitoring and health code verification are essential steps for workers in the Phase II expansion project to complete before entering the site every day. Although the current situation of epidemic prevention and control is gradually improving and the order of production and life is accelerating, as the second phase expansion project with a large personnel flow, we still insist on solidly implementing epidemic prevention and control work without slackening.

In addition to regularly distributing hand sanitizers, disinfectants, protective masks and other epidemic prevention materials, the command center of the Phase II expansion project has also continued to carry out disinfection work on workplaces and living areas, with good results in epidemic prevention.

As of now, the preparation work for completion and acceptance of the second phase expansion project's airfield project has begun; The basic installation of the luggage system, air conditioning, and boarding bridge in the terminal has been completed, and the interior decoration project has been completed by 40%; The supporting engineering circular road and bridge transportation system is gradually taking shape, and the Dongjinchang Road has entered the final stage, with half of it already functional and open to traffic.

It is reported that the design goal of Haikou Meilan International Airport Phase II is to meet the annual passenger throughput of 35 million people and the annual cargo and mail throughput of 400000 tons by 2025. After completion and opening up, it will not only provide hardware infrastructure support for Hainan's vigorous development of tourism and transportation of a large number of passengers, but also integrate various transportation modes such as aviation, railway, and road, establish an efficient and convenient transportation transfer system, create an aviation regional gateway hub for the Pacific and Indian Oceans, and assist in the construction of Hainan Free Trade Port.




Source: Haikou Net

Note: All accompanying images in the article are reposted online. Any infringement will result in deletion! Return to Xianji website to see more


Original link: https://www.xianjichina.com/news/details_190382.html